Construction of Rim
Drive
<<
Previous
|
Table of
Contents |
Next
>>
Segment 7-A (Rim Village to Diamond Lake Junction)
With roughly $250,000 allotted
for grading just shy of 6 miles between Rim Village and
the Diamond Lake Junction, BPR advertised for bids on
May 1, 1931. P.L. Crooks Construction Company of
Portland was awarded the contract and began work in June
by establishing their camp near the Devil's Backbone.
Work proceeded quickly from Rim Village, with roughly
one quarter of the job completed in only three weeks.
The contractor's workforce of
ninety men (increased to 125 by mid-July) soon began to
encounter rougher terrain, where blasting and other
means were needed to move more than 50,000 cubic yards
of rock per mile. Just the first four rock cuts (which
averaged 35' in depth) consumed over half of the
estimated 150,000 pounds of powder as needed for the
entire job. The remaining seven cuts were not thought to
be so difficult, with the exception of one running by
the Watchman Overlook that measured over 90' deep.
In early July, the NPS made
note that four steam shovels were working to widen the
existing road while "every effort" went toward retaining
"as much of the natural beauty of [this] section as
possible." One of the measures taken limited the
contractor to small quantities of powder when blasting,
thus throwing rock into the roadway rather than the
"right of way." This method facilitated more effective
debris removal by truck and reduced the length of fill
faces, while preserving vegetation. Crews dug trenches
at the toe of fills to hold rocks from rolling further
down slope, and protected tree trunks with planking to
prevent injury from flying rocks. The contractor later
modified this practice through using worn truck tires,
placing one on top of the other around tree trunks. This
practice protected the trunk on all sides and allowed
crews to move the tires from one rock cut to another as
blasting progressed.
With all of the anticipated
blasting and rock removal, the NPS tried to warn
potential visitors about finding "some inconvenience"
and advised them to take the "east drive" in preference
to the west, even forecasting that the latter might be
closed for two week intervals beginning in August.
Despite this gloomy prediction, traffic flow on the west
rim remained "unhampered" throughout the season. Much of
the reason lay in constructing contiguous cuts and fills
in half sections, thereby permitting the passage of
vehicles. The project even allowed inauguration of the
Rim Caravan that summer, a regularly scheduled excursion
conducted by ranger naturalists that featured half of
its sixteen stops within the first 6 miles of road
beyond Rim Village.
By November 1, the job stood
at approximately 75 percent complete. This was despite
utilizing "as much hand labor as possible" to help
alleviate local unemployment problems. Two of the
heaviest cuts (one being around the Watchman Overlook)
remained for the 1932 season, yet the four months spent
on the job that summer did not quite bring it to
completion. Aside from some finish grading, most of the
remaining work related to landscape items. These,
however, remained limited in comparison to subsequent
grading contracts on other segments of Rim Drive. Old
road obliteration, for example, took place only where
abandoned sections touched on the new roadway.
Consequently, long pieces of the old Rim Road remained
plainly visible from high points such as the Watchman or
Hillman Peak.
This somewhat patchy approach
to landscape work also applied to the masonry items.
Whereas the contractor saw the culvert headwalls to
completion, only 250 yards of retaining wall and
guardrail were built. The latter work during the grading
contract came on the Watchman grade, where the NPS had
the most concern for safety. The need for additional
masonry wall along the road margins commanded sufficient
attention, such that the NPS referred to the next
contract as "Surfacing and Guardrail" when BPR
advertised for bidders in the summer of 1932.

West Rim
Drive is shown below (at left); the route of its
predecessor, the old Rim Road-- is now part of a
hiking trail along the rim. |
Although a surfacing contract
was awarded that fall, the successful bidder (Homer
Johnson Company of Portland) did not begin work until
August 1933 due to a record snow year. Barely two months
elapsed before the onset of winter suspended the job,
but unusually dry conditions allowed work to resume in
April 1934. It proceeded quickly enough for final
inspection of the surfacing to take place less than six
months later, mainly because the Johnson plant produced
550 tons of crushed rock per day.
A subcontractor, Angelo Doveri
of Klamath Falls, handled construction of the
guardrails. The resident landscape architect for the
season of 1934, Armin Doerner, described a slow start
during the late spring and early summer. He found that
different workmen each tried to express "his own ideas
about masonry," so it proved difficult to obtain "a
uniform type of wall" at first. When Doerner and the BPR
inspector finally agreed on the style wanted, the work
improved and proceeded at a faster pace. Sargent and
Doerner agreed to the locations of the walls, starting
with two relatively short ones near Rim Village and
another of some 500' in length at the Discovery Point
Overlook. By the final inspection in October, Doerner
thought the guardrails had a "very pleasing" appearance
aside from some imperfections. One was the trimming,
which made it difficult to obtain the specified amount
of weathered surface. Achieving the desired variety of
color in the walls became problematic when quarrying all
of the rock from the same locality.
The surfacing contract did not
include enough funding to provide masonry guardrail to
line the outer edge of each viewpoint, nor at the road
margin where 7-A had been located along a precipice.
Engineers tried to mitigate the latter problem by
banking the road toward the inside slope, as they did
along parts of the Watchman grade. The lack of
guardrail, however, became even more noticeable at the
Diamond Lake Overlook near Hillman Peak, a viewpoint
whose outer edge had initially been delineated with
irregularly spaced boulders having jutted ends. Its
appearance put this substation markedly out of character
with the rest of Rim Drive, so Lange prevailed on a CCC
crew who partly buried treated logs to line the outer
edge of the overlook in 1936. Each of the logs was hewn
at its ends to provide better visual transition when
spaced at regular intervals, since Lange hoped to bring
weathered boulders to the site and alternate them with
the logs. This treatment represented something of a
stopgap measure in the absence of masonry guardrail, but
it functioned as a better alternative than more crude
barriers.
Doerner criticized another
flaw in the surfacing phase of road construction in 7-A
in 1934. He took aim at certain daylighted cuts (ones
where equipment created open areas devoid of vegetation)
that became pullouts once they had been surfaced with
crushed rock. Not only were these unintentional
additions superfluous since plenty of stopping places
had been provided in the plans, but their appearance was
so unsightly that Doerner wanted the surface material
removed. He wrote that these flat areas should be
allowed to grow over with a natural ground cover, since
apparently there was no way to haul additional material
to these sites and obliterate the pullout by bank
sloping. The only obliteration stipulated in the
surfacing contract for 7-A aimed at removing the quarry
and crusher site from view, along with cleaning up the
camp located near Devil's Backbone. Johnson's reluctance
to do the latter may have stemmed from plans that
targeted some of the camp buildings being used for the
paving phase of road construction during the summer of
1935.
BPR awarded the contract for
paving 7-A to J.C. Compton of McMinnville, who then
started giving the road a bituminous surface treatment.
This job consisted of several steps, with the first
being the spreading of aggregate (or "prime coat," as
Lange called it). The laying of a bituminous "mat" of at
least 3" in depth came next, one extending over the
entire roadway and parking areas. Lange thought the
black color of the mat fit "well with the surrounding
country," and remarked how it presented a "fine
appearance in relation to existing natural features."
The last step in the paving contract started with
application of a seal coat or wearing course to a width
of 18' in accordance with federal highway standards of
1932. Its black color was then altered with a fine coat
of rock, which upon rolling and brushing, yielded what
Lange called a "uniform medium gray color." The
contractor completed this step on segment 7-A by October
1935, but returned the following year to finish a
related paving job (on the North Entrance Road, route 8)
and restore the site of his construction camp located
near Devil's Backbone.
Road striping did not come
until 1938, but was in accordance with earlier advice
from Lange, who advised that a "yellow, or similar
colored line" could serve the purpose. He did not favor
a continuous line over the entire road, but rather use
of the stripe on curves or other areas in need of such
marking to insure the safety of motorists.