Construction of Rim
Drive
<<
Previous
|
Table of
Contents |
Next
>>
Segment 7-B (Diamond Lake Junction to Grotto Cove)
Pre-advertising for bids on
grading the stretch of road from the Diamond Lake
(North) Junction to the point half a mile past Wineglass
took place in the fall of 1932. Insufficient funding
prevented letting a contract until September of the
following year, at which time the award went to the firm
of Von der Hellen and Pierson of Medford. The
contractors went to work in October 1933, but BPR
suspended the job upon the first snowfall several weeks
later. In contrast to what NPS crews accomplished prior
to the contract award in segment 7-A, the clearing and
grubbing of 7-B became the contractor's responsibility.
They moved ahead on the basis of plans calling for a
roadway of 22' with a ditch 3' wide. Another contract
had to be let, this time to Dunn and Baker of Klamath
Falls, in order to widen the roadway another 2'. This
change was the result of a visit to the park by
Secretary of the Interior Harold Ickes in July 1934.
Much of the work performed on
the first grading contract in 7-B took place during the
long summer season of 1934. Von der Hellen and Pierson
set up camp near the Wineglass at a secluded spot where
water could be pumped from the lake some 650' below
them. In contrast to grading segment 7-A, the grading
contract for 7-B required comparatively little blasting
and hauling of rock. The contractors could thus use
caterpillar tractors and scrapers in handling the pumice
material. They had some assistance from the final
located line that called for five tangents of various
lengths, but with several rock cuts required as part of
preventing overly heavy curvature in the alignment.
Doerner gave Von der Hellen and Pierson high marks for
not scattering stumps beyond the clearing limits (or
"right of way") when blasting stumps, despite the road
being characteristically close to the rim in many
places. He also commented on the care taken with dumping
rock at the ends of deep fills so that deep trenches at
the bottom of fill slopes might catch debris from
rolling any further. The contractors then used plenty of
soil to completely cover the rock at the bottom of such
fills.
Subsequent widening of the
roadway began in September 1934, but Dunn and Baker
found it impossible to take the same protective
measures. In many places crews brought the rock back up
slope by hand after it damaged trees. The road widening
meant that Von der Hellen and Pierson could disregard
some of the required bank sloping and shoulder rounding.
Similar to the previous grading contract for 7-A,
however, these contractors still had responsibility for
other kinds of landscape work. Doerner reported that the
masonry retaining walls and culvert headwalls in 7-B
displayed good workmanship during the long season of
1934, though completion of these items did not come
until the following summer.
Most of the old road
obliteration in 7-B came in 1935, when Von der Hellen
and Pierson hired a landscape foreman under Lange's
supervision. As resident landscape architect for the
NPS, Lange saw an obliteration program to be "of
immediate value to the natural appearance of new road
construction" because it went beyond planting the ends
of old road segments as was done during the grading of
7-A. With a crew of four to ten men, the landscape
foreman planted approximately 100 whitebark pine and
fifty lodgepole pine over 1.2 miles of old roadbed in
1935. The difficult growing conditions meant that some
75 cubic yards of soil covering was used in conjunction
with a scheme that included spreading duff and small
branches so as to eventually produce a "uniform" line of
planting "unnoticeable to all but those accustomed to
the old road location." Lange took a number of
photographs to show the effectiveness and appearance of
such efforts, as part of his plan to obliterate 10 miles
of old road. He estimated this multi-year project needed
roughly 5,000 trees as well as 2,000 loads of soil, and
required the services of two or three foremen and twenty
laborers.
Grading and widening the
roadway also necessitated what Lange called "special
planting" aimed at large slopes exposed by construction.
The foreman and his crew treated two sections of 7-B in
1935, with the first located near the Wineglass road
camp where they treated a cut slope with some trees and
dark soil so as to diminish the intensity of the vivid
red color seen from Cloudcap. Work began by digging
parallel trenches filled with mountain hemlock branches
to hold the "new soil" and aid establishment of trees
transplanted at the site. This procedure was also used
to conceal a white line created by grading near Steel
Point that could be seen from the Crater Lake Lodge.
Production of surfacing
material for 7-B started even before the successful
bidder, A. Milne of Portland, began opening a quarry
near the Wineglass road camp in September 1935. The
contractor set up a crushing plant there, an operation
that Lange described as well screened from the road. It
could produce a relatively large amount of material at
1,500 tons per day when running at capacity during the
short working season. Once the plant at the Wineglass
road camp produced sufficient quantities for both 7-B
and 7-C, virtually all of the actual surfacing with
crushed rock took place in 1936. With the paving of
those road segments not due until 1938, BPR advised the
NPS that maintenance crews should apply a light oil
treatment in the interim to prevent loss of the soft
rock quarried and processed for surfacing material at
the road camp.
Milne's subcontractor for the
masonry guardrails made good progress in only two months
on the job in 1935, completing almost half of the
stipulated 450 lineal yards in segment 7-B. Lange seemed
pleased with the pace at which work on the guardrails
proceeded, but he commented that the first sections of
wall built where the road first touched the rim east of
Llao Rock were not entirely satisfactory. Within a short
time, however, he remarked about how this item became
"exceedingly well done" and included photographs in his
annual report of some representative guardrails from
this road segment.
Failure to provide such
barriers, especially where the road ran close to a
precipice concerned Lange, though he did not cast blame
for the oversight. He instead called for the NPS or BPR
to provide some rule for such areas in future contracts,
whether the remedy lay in masonry wall or partially
buried logs in combination with seated boulders. Since
funds for additional masonry guardrail seemed out of the
question, logs treated with creosote of varying lengths
were placed to line road margins where the danger
appeared to be the most acute. Lange preferred logs to
alternate with boulders and produced a drawing to that
effect, but the BPR district engineer did not believe
that estimates in the existing advertised contract
allowed for the cost of gathering and placing boulders.
Lange nevertheless wanted spaces left between the logs
in order to allow for the future introduction of
boulders as part of a subsequent contract, so the
installation of these barriers proceeded accordingly in
1936. Logs were also used to define islands in what
Lange called "traffic control areas" at road junctions.
The surfacing contract provided for treating the Diamond
Lake Junction with partially buried logs having
chamfered ends and some planting once fine grading of
the site had been completed as part of the surfacing
contract.