Construction of Rim
Drive
<<
Previous
|
Table of
Contents |
Next
>>
Segments 7-C and 7-C1 (Grotto Cove to Kerr Notch)
Available funds for letting a
grading contract from Grotto Cove and the summit of
Cloudcap in September 1933, plus short-term uncertainty
over the L-line near Mount Scott, resulted in splitting
segment 7-C away from what was now called (for
contracting purposes, at least) 7-C1. The grading
contract for 7-C and the spur road to Cloudcap (4.4
miles in all) went to Dunn and Baker, who were also
awarded the contract for widening 7-B and 7-C in 1934.
It made for a smooth transition, especially since this
firm had the benefit of a long working season that year.
Clearing and grubbing were
included within the bid items for grading 7-C, just as
they had been for the previous segment. Other
similarities to previous grading contracts were items
like the masonry headwalls for culverts and the limited
amount of old road obliteration. Dunn and Baker
experienced more difficulty than Von der Hellen and
Pierson with rocks rolling beyond the toe of fills
during blasting operations. Some damage, for example,
resulted when in an accidental overcharge of powder sent
a large quantity of rock below a cut near Scott Bluffs.
Having to repair the damage made the most challenging
part of rough grading even slower, since the stipulated
light shooting had to be followed by construction of a
retaining wall. Superintendent Canfield described these
rock formations as difficult, but ones that the
contractors handled efficiently and in the same manner
as those in segment 7-A.
After completing most of the
items as part of widening 7-B and 7-C, Dunn and Baker
went to work during the summer of 1935 grading one of
two units in segment 7-C1. This section of 1.5 miles
extended from the Cloudcap Junction (where the spur road
to the summit diverges from Rim Drive) to Sentinel Rock.
Von der Hellen and Pierson, meanwhile, started grading
the other unit of 7-C1 (a section of 2.4 miles of road
between Sentinel Rock and Kerr Notch) that summer after
having finished grading in 7-B.
All the rough grading in 7-C
and 7-C1 meant that the amount of landscape work
accomplished during the 1935 season was relatively
small, apart from subcontractors finishing the culvert
headwalls and some planting related to old road
obliteration in the Cloudcap vicinity. Lange made a
point, however, of describing two associated problems
that rose to the top of his list to correct over the
following summer. One resulted from cuts where one side
of the cut was too low in height to be properly sloped.
He acknowledged that a number of landscaped parking
areas were necessary for visitors to enjoy the scenery
and make repairs to their vehicles if necessary, but any
proliferation of unintended parking areas detracted from
Rim Drive being able to harmonize with its surroundings.
Lange wanted these areas converted into slope banks
where at all possible, and then showed an example of the
recommended treatment in his annual report for 1936.
An even larger problem stemmed
from daylighting prominent viewpoints in 7-C for fill
material, thereby compounding the challenge of having to
obliterate old road on soils that tested virtually
sterile. Lange began making an argument for extensive
landscape treatment of what he began to call "parking
overlooks" in 7-C and 7-C1 as part of his season ending
report for 1935. He pointed to certain examples, such as
the excessive daylighting at Skell Head, in identifying
five localities for special landscape treatment as part
of a future surfacing contract.
Lange made preliminary
sketches of five parking overlooks, going somewhat
beyond what had become the standard treatment for
viewpoints along Rim Drive. In addition to masonry
guardrail to delineate the edge of the rim for
motorists, Lange added a bituminous walk running the
full length of the wall as well as a stone curb to
separate the viewing platform from parking. Each of the
five overlooks featured an island defined by a
combination of weathered boulders and logs so as to
protect a small amount of planting that consisted of
native shrubs and trees. He argued that the islands
helped to diminish the size of each of the daylighted
overlooks, thereby placing each of them into proper
scale in relation to Rim Drive. The islands also
provided greater safety by separating motorists using
the road from those leaving or entering each overlook.

Interpretive
marker and parapet wall at Skell Head.
|
After describing how the
stations located along Rim Drive might appear in his
season-ending report for 1935, Lange obtained topography
and other engineering data from BPR for the parking
overlooks over the following summer. Whereas segments
7-A and 7-B had so far represented missed opportunities
to properly develop the stations and substations along
Rim Drive through the contracting process, Lange wanted
to show what could be achieved at viewpoints located in
7-C and 7-C1. He included photographs in his reports of
progress made at four parking overlooks in 7-C through
the surfacing contract (the same one awarded to Milne
for 7-B) during 1936, with each showing how the masonry
guardrail looked in relation to logs used for
demarcating the islands. Although still in the rough
grading stage of construction, Lange anticipated similar
landscape treatments at four parking overlooks in
segment 7-C1. Rejection of bids for the 7-C1 surfacing
contract in the fall of 1936 proved to be an eventual
boon to the development of the parking overlooks, since
BPR subsequently doubled the amount available for
landscaping these viewpoints. The move reflected the
need to transport and place weathered boulders, as well
as the use of topsoil, peat, and fertilizers as soil
amendments prior to planting some 400 trees and 600
shrubs at the parking overlooks. Lange produced site
plans for seven overlooks located between the Wineglass
and Kerr Notch that were formally approved in December
1936 and then incorporated in the revised set of plans,
specifications, and engineering estimates used to
solicit bids at the end of June 1937.
BPR awarded the surfacing
contract for 7-C1 to the Portland firm of Saxton,
Looney, and Risley in July, with the job getting
underway in late August. The contractors made relatively
quick work of spreading a base course over the 4 miles
of this road segment, completing it in the fall of 1937.
The landscape component was only half finished by the
end of the season, even though the two foremen who
reported to Lange directed a crew of twelve laborers.
Planting required hauling topsoil and peat from "pits"
located near Park Headquarters, in addition to using 3
tons of fertilizer obtained in Klamath Falls. Lange
described preparation of the planting beds as a base of
peat, to be followed by placing shrubs or trees, with
topsoil and fertilizer put "around but not too close to
the root system." Duff was then scattered throughout the
immediate vicinity of the planting. Crews followed the
same procedure when planting at the parking overlooks
during the 1938 season, although this time they were
under the supervision of new foremen. They planted a
total of 625 trees, as well as 2,300 shrubs and plants
at the viewpoints over two summers.
The masons, meanwhile, added
to guardrail previously completed in 7-C by finishing
another 750 lineal feet of guardrail in 7-C1 that
season. They also continued to place what Lange
described as "excellent stone curbing" at the overlooks,
in addition to the weathered boulders indicated on the
site plans. Lange also assisted the masons by providing
a working drawing for steps leading to a trail at
Sentinel Point and a sketch for the stone drinking
fountain installed at Kerr Notch. The additional touch
of paving walks at four parking overlooks in 7-C came as
part of the paving contract awarded in June 1938 to
Warren Northwest, a construction company with regional
offices in Portland.
The contractor erected its
plant at the Wineglass road camp over the following
month, situating it so as to be equidistant from both
ends of a job that called for paving approximately 12
miles of Rim Drive between the Diamond Lake Junction to
the road summit atop Cloudcap. In contrast to the work
completed in 1936 along the 6 miles of 7-A, this
contract included paving "gutters" in accordance with
guidance developed by Thomas E. Carpenter, deputy chief
architect for the NPS. His work reflected a trend toward
shallower ditches requiring less maintenance, given that
the bituminous paving acted as a seal against run off
that might otherwise disintegrate surfacing material
used to protect a road's subgrade. The gutters were to
work in concert with catch basins or inlets connected to
culverts placed underneath the road at regular
intervals. For this contract the "invert" was set at 5"
below the seal coat, with an actual level depth of 3" in
the paved gutter. Lange commented that the gutters had
an "excellent appearance" in his report for September
1938, but the contractor returned in 1939 to do
additional sealing because cold weather the previous
fall caused some cracking.
With the paving contract
essentially completed, Lange used a number of photos in
his season-ending report for 1938 to show how landscape
treatments improved typical road sections in 7-B and
7-C. In contrast to the numerous landscape items left
unfinished in 7-A, both of the latter segments exhibited
good examples of old road obliteration, bank sloping,
and special landscape treatments such as adding dark
soil to reduce scars. Paving and placement of catch
basins in conjunction with the placement of backfill for
gutters seemed to signify that the new Rim Drive was
"rapidly becoming a reality," with all work projected to
be finished in the fall of 1940. Lange made a point of
depicting the finished parking overlooks in 7-C and 7-C1
since they demonstrated how to rehabilitate damaged
areas while properly developing the observation stations
and substations. The only thing missing from 7-C1 was
the paving, but it went to the top of Superintendent
Leavitt's funding requests for roads and trails
beginning in 1939.