Construction of Rim
Drive
<<
Previous
|
Table of
Contents |
Next
>>
Segment
7-D (Kerr Notch to Sun Notch)
Formal adoption of the
so-called "combination line" in December 1935 pushed BPR
to finalize plans to locate Rim Drive between Kerr Notch
and Sun Notch. Instead of "skirting" Dutton Ridge as the
official press release had claimed, the road location
required major cuts on both sides. The large amount of
excavation anticipated caused BPR to split 7-D into two
grading contracts, with 7-D1 originally projected to
encompass about 2.7 miles from Kerr Notch to a point on
the south side of Dutton Ridge where the road would
crest. The lowest bid on this first contract, one that
required a staggering 176,000 cubic yards of excavation,
was rejected in July 1936 since it was considerably
above the engineer's estimate. The need to make an award
within existing allotments led to another advertisement
for bids a month later, this time with the distance of
7-D1 reduced to just over 2 miles. The contract went to
Orino Construction of Spokane, who then set up camp on
Sand Creek in Kerr Valley and began its clearing
operations. Dunn and Baker, meanwhile, won the contract
for grading the next 2.9 miles of road. This included
both 7-D2 (which ran from the end of Orino's contract on
Dutton Ridge over to Sun Notch) and the adjoining 7-E1.
They could do little more than establish camp on Vidae
Creek before the construction season came to an end.
With the grading contract for
7-D1 estimated to be some 70 percent excavation, Lange
warned that the job required extremely careful measures
to protect trees. He made special reference to fill
material, which could escape in areas dominated by long
and continuous slopes. With blasting operations imminent
in July 1937, Lange described how the ground cover of
willows and other plants located beyond the grading line
were already being struck by falling material. It upset
him enough to write that the location for 7-D should
never have been approved because of the resulting
damage, though this sentence was subsequently scratched
out on his report.
Blasting by Orino over the
next few weeks gave Lange and resident engineer Struble
almost opposite impressions. Whereas Struble described
the contractor's progress as unsatisfactory due to
extreme care taken with type "B" excavation, Lange wrote
about Orino permitting a number of excessive shots not
in accordance with instructions from BPR. Slides
traveled, he observed, far below the necessary line of
repose. This damaged trees to such an extent that the
majority had to be removed. Crews pruned trees where
blasted material hit their tops, while cuts were treated
with creosote if the damage did not require removal.
Lange gradually prevailed upon Struble to require Orino
to protect trees in subsequent blasting by shooting with
less powder. The difficulty of grading in such terrain,
however, made complete protection "almost impossible,"
even when trees from the roadway were placed against
those situated below the grading line.
Cuts represented another
aspect of rough grading that detracted from what Lange
had described as an area that was "originally admired
for its stately and primitive character." One of these
measured approximately 145' to the roadbed from the
crest of the cut, causing falling rocks to be a constant
danger due to so much loose material on Dutton Cliff. An
"epidemic" of minor accidents kept the park physician
busy, such that Leavitt noted that the men hired by
Orino seemed especially prone to broken ribs. Not only
were equipment operators vulnerable, but also those men
working on several hundred feet of hand placed retaining
wall. Lange described the wall as necessary in order to
give the roadway its designed width of 24'. He
especially liked how it blended with the surroundings
from the point above Kerr Notch, writing that the
massive rocks obtained in the cuts were well selected
for color and uneven faces.
The difficulties encountered
by Orino in grading 7-D1 during the 1937 season (his
crews consumed more than 60 percent of the allotted
time, yet completed only a third of the job) contrasted
markedly with how Dunn and Baker fared in 7-D2. The
south and west sides of Dutton Ridge and the area above
Sun Meadow required about 50 percent rock work, but the
contractors found it easier than what engineers had
estimated. Progress on grading 7-D2 stood at almost full
completion by October 1937, with only finish grading and
some landscape details expected for the following
season. Lange identified "very little" damage to trees,
either in burning those cleared from the roadway or
during grading operations. He described how log cribbing
used on this job reduced injury to standing trees and
noted that the contractors retrieved all of the rocks
passing beyond the desired point of repose at the toe of
each fill.
Lange seemed particularly
pleased with the masonry features along 7-D2, making
special reference to what later became known as
"spillways," in his season-ending report for 1937. He
included a photograph showing a floor laid to catch run
off derived from continual seepage on slopes, to be
connected with culverts as part of cross drainage. The
masonry component of this grading contract was otherwise
limited to building culvert headwalls, most of which
appeared along the south side of Dutton Ridge, where
snowmelt created seasonal drainage.

East Rim
Drive along Dutton Cliff with the Pinnacles Road
below it. |
Guardrails were to be part of
the surfacing contract, but Lange could not help
noticing how the road location he so heavily criticized
opened some fine views along this section of Rim Drive.
After securing topographic data from BPR, he prepared
sketches for parking areas like Sun Notch along 7-D2.
The parking areas became part of finish grading in 1938,
as did additional bank sloping and covering a portion of
the scar on Sun Grade with dark soil.
Orino completed most of the
rough grading in 7-D1 during the 1938 season, but all of
the time allotted for the contract had long since
elapsed. A somewhat sympathetic Lange explained that the
number and size of the retaining walls needed along the
eastern side of Dutton Ridge justified a contract
extension. The hand placed walls begun in 1937, for
example, were placed on each end of a masonry wall to
span one of the fills. Others required masonry walls
roughly 25' in height, with one noteworthy example
exceeding twice that measurement.
The fills settled sufficiently
for construction of masonry guardrail to move forward as
part of the grading contract for 7-D1 during the 1939
season. Lange expressed some hesitancy in allowing Orino
to extract rock from the Watchman for some 3,000 lineal
feet of guardrail, but he and Leavitt relented once the
contractor agreed to use a heavy crane for obtaining
material. This method eliminated new "tote" roads and
other construction impacts associated with reopening a
quarry that had been "restored" since 1936. Struble
thought the guardrail component was especially well
organized during the summer of 1939, especially since
the masons had completed the job by August 20. Lange saw
the rock selection and workmanship as very good,
commenting on how the guardrail had been introduced to
"best advantage, resulting in varying curves to fit the
terrain."
In his season-ending report
for 1939, Lange called the provisions for protecting the
landscape in 7-D1 "commendable" despite his misgivings
about the road's location. Damaged trees were removed,
pruned, or had cuts created by flying rock treated with
creosote. Other measures included special planting on
slopes below the fills so as to reduce future damage
from rock fall on the East Entrance Road, as well as
some fairly extensive bank sloping and regrading as part
of old road obliteration around Kerr Notch. Several
small items had to be deferred to future contracts, with
one example being Lange's proposal to plant the areas
adjoining each of the three spillways in 7-D1 so as to
better "reproduce" the natural stream bed adjoining the
road.
After inviting bids for
surfacing 7-D along with segment 7-E in August 1939, BPR
awarded the contract to Orino several weeks later.
Although largely devoid of landscape items, this job
included a provision for building more than 300 cubic
yards of masonry guardrail in 7-D2. The contract
centered on producing aggregate for the next two phases
of construction, so Orino set up a rock crushing plant
in June 1940 not far from the camp he occupied along
Sand Creek during the grading contract.
The nearby quarry yielded
enough rock for a base and top course of surfacing
material and some 27,000 tons of aggregate to be
stockpiled for future paving of the remaining segments
of Rim Drive. This "leg up" approach to paving left a
mere $70,000 needed for plant mix, labor, and equipment
to place a bituminous surface on segments 7-C1, 7-D, and
7-E. The paving job represented the final piece after
the government had spent a little more than $2 million
in contracts for building Rim Drive since 1931.
Difficulties with obtaining equipment for the rock
crusher, however, hindered progress on the surfacing
contract so that production of aggregate was not
completed until September 1941. In the mean time, the
contractor applied a "double prime bituminous surface
treatment" to the unsealed roadbed as a temporary
measure for carrying traffic until such time that actual
paving took place.
American involvement in World
War II allowed for only enough funding to remove slides
that resulted during the winter of 1941-42. With paving
put on indefinite hold, the suggested treatment of the
parking areas became a forgotten item. Lange used a
photo to depict one such stopping place in 7-D1 as part
of his final report at Crater Lake for 1939. With the
masonry guardrail completed, he remarked that the
parking areas should be given a lighter color finish
than that of the road.