Construction of Rim
Drive
<<
Previous
|
Table of
Contents |
Next
>>
Segment 7-E (Sun Notch to Park Headquarters)
The initial P-line run by BPR
assigned segment 7-E to a route linking Sun Notch with
Rim Village, but the subsequent adoption of a
"combination line" led to dividing the segment into two
pieces for contracting purposes. A sort of "middle line"
connected Sun Notch with Vidae Falls and became 7-E1,
while 7-E2 roughly corresponded to the old "low line"
running from Vidae Falls to Park Headquarters. Some
adjustment to the road mileage stipulated in the
respective grading contracts was still necessary,
however, due to the uncertainty that existed in 1936
over what the site development around Vidae Falls might
entail. This resulted in shortening the contract for
grading 7-E1 by four tenths of a mile so that it could
be combined with 7-D2 and then advertised for bid.
Dunn and Baker completed all
of the rough grading and most of the finish portion of
the contract in 7-E1 during the 1937 season. Just over a
mile in length, 7-E1 turned out to be relatively easy
work. In running above the western margin of Sun Meadow
and along the bottom of a slide on the flank of
Applegate Peak, the new road provided Lange with an
opportunity to show a particularly good example of bank
sloping through a heavy rock slide. The only other
landscape item that he or the superintendent noted in
7-E1 concerned the need to obliterate an old "motor
trail" improved by the CCC in 1933, one that started
toward Sun Notch where the old Rim Road crossed Sun
Creek.
BPR awarded the contract for
grading 7-E2 to E.L. Gates of Portland in October 1937.
This meant that work on the final 3.3 miles of Rim Drive
began the following spring, with the nagging question of
whether to construct a bridge or use fill to span Vidae
Creek finally resolved. Gates constructed the fill over
the following summer, which included placement of a pipe
culvert with stone headwall at both ends. Lange
estimated the contractor to have completed 90 percent of
the rough grading in 7-E2 that season. Photographs in
his final report for 1938 showed ditch and slope
treatment along one stretch of road, some old road
obliteration through bank sloping, and placement of what
he called a "culvert drain" with rough stone pavement
less than a mile from Park Headquarters.
Aside from planting, most of
the remaining items in the grading contract pertained to
completing the road connection below Vidae Falls to the
proposed Sun Creek Campground. A need to relieve
pressure on the campground at Rim Village drove
selection of new sites, such as Sun Creek, away from
where the lake could be seen. As one of several
satellite areas, NPS officials hoped that a new
campground below Vidae Falls might provide an attractive
alternative to the problems associated with overuse in
Rim Village. Superintendent Leavitt liked the Sun Creek
site, but did not want it opened for use by visitors
until properly developed so as to avoid damage to the
trees and ground cover. The first step toward building
the campground came in the form of a serpentine road
going down a quarter mile from Vidae Falls to an area
that once served as an informal picnic site on the old
Rim Road. A bank slope constructed at its intersection
with the Rim Drive served the dual purpose of reducing
the campground road's presence to motorists traveling
the main route, yet also afforded sufficient visibility
from one road to the other.
Plans for a stopping point
beneath the waterfall called for widening the road fill
on the upstream (or northern) side of Rim Drive, so as
to allow for parallel parking. Installation of a stone
drinking fountain at this parking area came in July
1939, but construction of additional landscape features
had to wait until the subsequent surfacing contract was
let. These included building a raised walk 4' wide in
front of Vidae Falls, which was separated from the
roadway by a stone curb. Just as they had in 7-D, Lange
and other NPS landscape architects anticipated
distinguishing the Vidae Falls parking area from Rim
Drive through the use of pavement having a rougher
texture and somewhat lighter color finish.
Introduction of the fill
spanning Vidae Creek constituted what Lange termed as
the "major landscape problem" in 7-E2. He reported that
it required more than 1,000 yards of topsoil in
preparation for planting the entire slope as part of
making the fill conform to surrounding terrain. This
effort required more than 5,000 plants, shrubs, and
trees. Al Lathrop, formerly one of Lange's assistants
for CCC work, had charge of a crew numbering ten men and
paid by the contractor. They needed sixteen days to
plant a mix of species that included willows, mountain
hemlock, huckleberry, purple-flower honeysuckle
(twinberry), and spirea. A sprinkling system was needed
so that the plantings on the fill could initially be
watered every day, then two or three times per week
until early autumn. Lange described the source of water
as a "reservoir" built at the "head" of Vidae Falls,
located about 100' above the fill and out of sight from
Rim Drive. From there a 3" line was placed to one side
of the falls and connected to smaller lines spaced about
30' on centers across the planted slopes of the fill. He
estimated it might take two or three seasons for the
planting beds to provide the desired effect.
Leavitt expressed some
satisfaction in writing to Cammerer that all grading
contracts let in conjunction with building Rim Drive
were finally complete as of September 1939. Lange
mentioned this milestone in his season-ending report for
the year and optimistically projected the surfacing
phase to be finished in 1940, with the paving to follow
in 1941. The surfacing of 7-E did indeed come about over
the following season, but the funding request for paving
this road segment languished throughout World War II and
for more than a decade afterward. The NPS simply had to
make do using oil and asphalt treatments aimed at
protecting the subgrade and surfacing material of this
road segment.


Parapet of
the Sinnott Memorial. |