NPS and BPR Collaboration on Approach Roads
<<
Previous
|
Table of
Contents |
Next
>>
Route
1 (West Entrance to Annie Spring)
Work continued on what had
formerly been called the Medford Road in 1926, so that
the macadam surfacing had been completed by the second
week of August. The finished roadway now had a graded
width of 18' shoulder to shoulder, with a surfaced width
of 14'. Thomson commented on the high standard of the
road, particularly once removal of construction debris
had taken place and log guardrails were installed where
needed. Finding a wearing course that did not require an
annual application of road oil took the next two
seasons. NPS engineer Ward Webber wrote about the
bituminous surface treatment (paving) used in 1927, one
where insufficient mixing of oil with aggregate resulted
in the wearing course lacking uniform texture. He noted
that some portions were too lean, while others contained
too much oil, thus necessitating the reprocessing of
this asphalt material when the surface began to fail
under traffic. The NPS achieved better results in 1928,
though it took supervision by T.R. Goodwin (a road
oiling expert on loan from the California State Highway
Commission) to obtain the desired texture and color.
Minimal post construction work
(such as patching, widening of bank slopes, and fine
grading) by NPS crews took place along this route during
the 1930s, though funding through the Civilian
Conservation Corps (CCC) paid for development of a small
public campground on the north side of the road crossing
at Whitehorse Creek. CCC enrollees built a water system
and two latrines there in 1934, but the site was
abandoned after the 1941 season. This came in response
to a proposal for a new, but modest campground to be
located at the West Entrance, where the NPS planned to
add a ranger residence, comfort station, and replace the
checking station. Available funding limited this
development to a portable kiosk that served as a
checking station beginning in 1946, with accommodation
for seasonal employees staffing consisting of an
unsightly shack hidden among the trees a few hundred
feet away.
The proposal by Superintendent
E.P. Leavitt for the road to be reconstructed over its
entire length, a project aimed at producing a roadway
32' wide with a surfaced width of 24', had to be put on
hold during World War II due to lack of funding. For the
next decade after the war ended in 1945, Leavitt and his
successors had to be content with much smaller amounts
aimed at maintaining ditches and patching the paved
surface. This type of funding did little to stave off
further deterioration, as the park's chief ranger
described the road as old and poorly drained in 1949,
such that the wearing course was badly cracked and
weathered.
The road's condition hardly
improved over the next two decades, given how one of
Leavitt's successors described it in 1964.
Superintendent Richard Nelson found extensive failures
in the base (composed largely of pumice) and pavement,
but also criticized how the roadway's width of 18'
lacked adequate sight distance on the numerous curves.
Snow removal posed difficulties for drivers on such a
narrow road, since the initial plowing produced windrows
that substantially reduced driving width during much of
the winter. Steep grades and sharp curves on two
sections also contributed to the road accounting for
some 65 percent of all automobile accidents within the
park.
Engineers with the Federal
Highway Administration (lineal successor to BPR) renewed
their discussions with NPS officials about road
improvements in November 1967. Everyone agreed about the
necessity of widening the roadway to obtain lanes 10'
wide, so the meeting focused on two proposed
realignments. One involved a preliminary road design of
1961 that called for a tangent at the crossing of
Whitehorse Creek, but the NPS rejected that idea in
favor of a more curvilinear alignment that better
matched the agency's road standards of the time. More
consideration was given to bypassing the Whitehorse
crossing altogether with a new road location.
Preliminary data indicated the possibility of going
around Whitehorse Bluff in traversing the Cascade
Divide, thereby avoiding the existing reverse curve with
its two tight radii on either end. Park Superintendent
Donald Spalding, however, feared the damage to timber
and wildlife habitat certain to result from such a major
realignment. He opted for improvements within the
existing alignment, pointing to how the disadvantage of
the reverse curve could be offset with curves having a
radius of 400' on either end.
Road reconstruction finally
began in October 1972, with the initial contract aimed
at widening the 2.4 miles between Whitehorse Creek and
the top of the Cascade Divide. It also addressed the
upper end of the reverse curve, where a large number of
vehicle accidents had occurred due to the abrupt change
in alignment. Project design called for wider lanes and
some superelevation, though the FHWA engineers doubted
that the improvements would result in substantially
fewer accidents because the topography did not permit
sufficient transition time for drivers to lower their
speed.
Reconstruction went forward
despite the problematic reverse curve, with completion
of the initial contract in September 1974. Widening and
reconstructing 2.9 miles of road west of Whitehorse
Creek started the following summer, so that final
inspection took place in July 1976. Several paved
parking areas were added along the route as part of both
contracts, though only one of them provided visitors
with a scenic vista. This came at Elephant's Back, where
parking areas on both sides of the road allowed those
who stopped a glimpse of Castle Creek Canyon.