Postwar Changes
<<
Previous
|
Table of
Contents |
Next
>>
Segment 7-B (Diamond Lake Junction to Grotto Cove)
Even if wayside exhibits
seemed to be the most ubiquitous addition resulting from
Mission 66 to Rim Drive, they remained scarcely in
evidence along the northern part of the circuit. One of
these interpretive devices could be seen at the
so-called Cleetwood "backflow," in the masonry
guardrail, across from where wind erosion on the cut
slope created during rough grading had resulted in
chronic raveling. The other wayside exhibit attempted to
convey the "story" of soil at Palisade Point, but in a
somewhat secluded location below the masonry guardrail.
Both picnic areas in segment
7-B followed a standardized road loop designed by the
resident landscape architect, John S. Adams, in March
1957. These sites were placed just over a mile apart
that summer, with another five tables installed down
slope of the parking lot for Cleetwood Cove in 1966. The
latter possessed the largest number of tables at any
picnic area on Rim Drive, even though it remained the
most difficult one for visitors to use. In addition to
the walk needed for amenities like toilets and garbage
cans situated at the parking area, the site lacked
surfaced paths and shade during the midday hours.
Development of a new trail to
the lakeshore at Cleetwood Cove with associated parking
came in response to the difficulties associated with an
existing trail from Rim Village. In addition to the
existing trail beginning some 900' above the water,
increased annual visitation to the park after World War
II made parking for boat trips and other activities on
Crater Lake an additional source of congestion at Rim
Village. Cleetwood Cove, by contrast, offered a southern
exposure (thereby eliminating much of the hand shoveling
required to open a path to the water each spring) and a
potential trailhead only 700' above the lake.
Construction of a new trail began in July 1958 so that
it became passable the following summer, but regrading
of steep sections and other work delayed full completion
of this day labor project until September 1962.
Parking at the Cleetwood Cove
trailhead initially consisted of simply widening the
road shoulders, but this solution quickly became
inadequate. The resident landscape architect, Joseph T.
Clark, produced a site plan in July 1961 that called for
a parking lot holding 100 cars. He proposed an assembly
area at the trailhead, one to be separated from the road
by metal guardrail. The plan also called for an
elongated parking area across Rim Drive from the
trailhead, oriented perpendicular to the road instead of
parallel. With an adequate entranceway, the parking lot
site would also be large enough to allow development of
a picnic area with some thirty tables or even a
campground. The initial plan called for a plumbed
restroom (comfort station) and septic system, though
this facility and the proposed drinking fountains
depended upon locating a supply of water. In the absence
of springs or other sources, contractors began drilling
a well in 1962. It remained dry even after a second
attempt at locating a potable water supply three years
later.
Grading the lot above
Cleetwood Cove began in the fall of 1961, but lack of
water effectively limited development of amenities other
than parking to portable toilets and five picnic tables.
These facilities became inadequate as the number of boat
tours increased over the next two decades, so landscape
architect Joe Dunstan sketched several alternatives
aimed at relieving poor circulation and overcrowding in
1991, primarily as a starting point in design. Little in
the way of changes resulted from this effort, with the
only additional development at the site resulting from a
spillage problem associated with fuel delivery to the
tour boats. The Fee Demonstration Program thus funded
construction of a fuel transfer building situated
between the parking lot and Rim Drive in 1998.