Service Roads
<<
Previous
|
Table of
Contents |
Next
>>
Park Headquarters
Of the three service roads at
this site, the oldest connects a utility area or
maintenance yard with an administrative plaza situated
at an entry point with the Munson Valley Road. This road
also extends uphill from the administrative plaza and
provides vehicular access to a residential area built
with the intention of housing permanent NPS employees
during the summer season. At the south end of the
maintenance yard is another service road, a one-way loop
serving the residential area for temporary NPS employees
called "Sleepy Hollow." Across the Munson Valley Road
from Sleepy Hollow is the park's largest residential
complex, "Steel Circle." The road through it (Route 21)
consists of an outer loop where housing units were
located and an inner access that allows employees to
reach a building used for social functions and
gatherings.
Metamorphosis of what the Army
Corps of Engineers initially called "Camp 2" began in
1926, when the NPS built a warehouse and incorporated
stone masonry in its ground floor walls. This type of
construction immediately gained favor over earlier log
structures and became the preferred mode of construction
as the headquarters development expanded over a wider
area over the next seven years. The need to establish a
defined circulation system quickly became evident in the
wake of largely unconfined vehicular access to the site.
Grading of a service road to
connect the new administrative plaza with both the
utility and residential areas took place in 1933, with
all excavation done by hand to maximize the numbers of
men hired on this public works project. With most of the
grading completed that fall, laborers began surfacing a
portion of the roadway with 4" of crushed rock obtained
from a contractor who used a preexisting quarry located
about 5 miles from Park Headquarters. A short
construction season dictated that the contract had to be
completed in 1934, though subsequent settling under
traffic meant surfacing needed water, then be mixed, and
re-laid. The NPS let another contract for crushed rock
in 1935, so that this material could be integrated with
emulsified asphalt and spread roughly 1" in depth. It
was then rolled, and the process repeated twice more
before motorists began to use the road surface.
Some rough grading of a
service road from the utility area to Sleepy Hollow
began in 1933 as part of building the first five cabins
there for temporary employees. They appeared on both
sides of the road and were joined by three additional
structures in 1936. Finish grading, surfacing, and
paving took place over the following summer to the same
specifications as the service road through the
administrative plaza. Lange added two parking areas
along the Sleepy Hollow road in 1937 as part of
accommodating employees still housed in tents. The
parking areas disappeared when the utility area expanded
in 1957, an undertaking that included establishing a
road connection between it and the new residential area
to be built across the Munson Valley Road. Piecemeal
removal of cabins in Sleepy Hollow started in 1984 and
continued over the next five years so that a new housing
area for temporary employees could be constructed on the
site in 1990. Contractors realigned the service road as
part of the project so that new structures were situated
on the inside of a paved access loop.
Grading of the road through
the Steel Circle housing area occurred in 1956 as a
precursor to building a number of units largely
consisting of duplexes with flat roofs. A portion of the
site had once been used as a landfill, so the contract
included grading the original access road from Rim Drive
in addition to creating a main entrance from the Munson
Valley Road. The former connection did not last long,
due to fears that visitors might unduly disturb
residents, so the road in Steel Circle has only one
entry point. Contractors surfaced this road in September
1957 so that paving could be completed prior to the end
of the construction season.