ALTERNATIVES
<<
Previous
|
Table of
Contents |
Next
>>
PERMIT AND CONSULTATION REQUIREMENTS
No permits would be required for the no-action alternative.
The following approvals and permits from jurisdictional agencies would be
required before either of the action alternatives could be implemented:
-
Oregon SHPO – Concurrence that no historic properties would be adversely
affected and that effects from the project on historic and archeological
resources have been taken into account in accordance with section 106 of the
National Historic Preservation Act.
-
Service consultation regarding threatened and endangered species, in
compliance with section 7 of the Endangered Species Act of 1973, as amended.
-
Permits from the U.S. Forest Service would be required for the use of quarry
materials and for hauling quarry materials over roads.
-
Oregon Department of Environmental Quality Basic Air Containment Discharge
Permit (OAR 340-216-0020, Table 1, Part A) for the asphalt plant and rock
crushing operations.
-
Oregon Department of Environmental Quality, National Pollution Discharge
Elimination System Stormwater Discharge Permit #1200CA.