ALTERNATIVES
<<
Previous
|
Table of
Contents |
Next
>>
ALTERNATIVES CONSIDERED BUT DISMISSED FROM DETAILED ANALYSIS
Figures 7, 8, and 9 illustrate three additional options that were considered for
the realignment of the switchbacks. In options 1 and 1A, the lower switchback
alignments would cut into the hill on the east side of the road. These two
options require approximately 2,700-square yards (option 1A) to 3,900-square
yards (option 1) (0.6 to 0.8 acre, 0.2 to 0.3 hectare) additional area of
disturbance than alternative C. The area of disturbance would come within 213
feet (65 meters) of the proposed wilderness boundary. These options would also
make snow removal more difficult than the current conditions, and potentially
lead to more rock and snow slides. Therefore, these two alternatives do not best
meet the purpose and need for the project and were dismissed from further
consideration.
Although option 4 would create 1,190-square yards (0.25 acre, 995-square meters)
less new disturbance than alternative C, this option would require the removal
of more mature/large trees than alternative C, and would require a grade of over
7% making the road steeper than current conditions and possibly creating new
safety hazards. Therefore, this alternative does not meet the purpose and need
sufficiently for the project and was dismissed from further consideration.

FIGURE 7. OPTION 1 — ALTERNATIVE CONSIDERED BUT ELIMINATED
[NPS-DSC\OCT02\106\20137]

FIGURE 8. OPTION 1A — ALTERNATIVE CONSIDERED BUT ELIMINATED
[NPS-DSC\OCT02\106\20138]

FIGURE 9. OPTION 4 — ALTERNATIVE CONSIDERED BUT ELIMINATED
[NPS-DSC\OCT02\106\20139]