Saturday, July 22
The US Geological Survey (USGS), C&C Technologies, Inc. (C&C),
and University of New Hampshire (UNH) groups all arrived at Crater Lake National
Park on Saturday, July 22. We all met with the National Park Service (NPS)
personnel and were told that the commercial helicopter contracted by the NPS for
our deployment had not been released from fire-fighting duties in Montana. The
NPS was working on another commercial helicopter operator as well as the
possibility of using a military helicopter as a contingency. The contracted
helicopter company (Erickson Air Crane) had concerns about our estimated weight
of the boat and they required us to have accurate weights on the boat and the
equipment van.
Sunday, July 23
We dispatched the boat to a crane company in
Medford, OR and the boat and the equipment van were weighed using a NPS scale
hung from a mobile crane. The boat and equipment van were then trucked to Crater
Lake NP. Sunday afternoon was spent unpacking the equipment van, weighing each
item in it, and then re-packing the van. In the late afternoon we were informed
by NPS that a Monday helicopter lift was not possible but Tuesday morning
remained a possibility.
Monday, July 25
Early Monday morning we were informed that the
commercial helicopter would not be released from fire-fighting duties so the NPS
immediately began to inquire about the possibility of a military helicopter. By
Monday afternoon it appeared a high likelihood that a US Army Reserve Chinook
helicopter could be called in to lift the boat into the lake.
Tuesday, July 26
We were told by the NPS at a 0800 hr meeting on
Tuesday to truck the boat up to the rim of Crater Lake (Fig. 14) and prepare for
a military helicopter lift at about noon. At about 0900 hr we were told that the
military helicopter was in the air. However, at about 1100 hr we were informed
that that there would be a two-hour delay in the arrival of the helicopter. And
finally, at about 1600 hr we were told that there would be no helicopter lift on
Tuesday and that a Wednesday lift was even questionable. Apparently, someone in
the chain of military command in Atlanta, Georgia was holding up approval for
the lift.
Wednesday, July 27
|
 |
|
Figure 14.
RV Surf Surveyer leaving the Crater Lake NP
staging area on its way to the helicopter landing site. |
We were informed by the NPS early Wednesday
morning that the US Army authorities in Atlanta were unwilling to give verbal
approval and required signatures up their chain of command. They suggested this
process might take several days. By 1100 hr we were informed that there would be
no helicopter operations on Wednesday.
At this point, a discussion between C&C, UNH, and
USGS determined that, if the boat was not in the lake by darkness on Friday,
July 28th, then we would be forced
to terminate the operation and pack up and depart because the cost of standby
would begin to use operational funds. In addition, the multibeam, IMU, and
workstations, as well as C&C personnel were required back in Lafayette by C&C
Technologies for the mobilization of a class 1 research vessel in Hong Kong.
That decision was passed on to Mr. Mack Brock, NPS at 1200 hr.
Thursday, July 27
We were informed on Thursday morning that there
would be no helicopter lift on Thursday because of military red tape. However,
by late Thursday afternoon we were informed that there was a high likelihood
that a military helicopter would be available Friday.
Friday, July 28 (JD 210)
We were informed Friday morning that a military
helicopter had been dispatched to Crater Lake to lift us into the lake. The
helicopter arrived at 1415 hr and by 1530 hr the boat was in the water (Fig. 15)
and by 1600 hr the equipment van was on Wizard Island. The remainder of the day
was spent getting personal gear down the trail and setting up the field station
on Wizard Island (Fig. 16).
|
 |
 |
|
Figure 15. RV Surf Surveyor being lowered onto Crater
Lake. |
Figure 16. Equipment van landing
on Wizard Island. |
Early Friday morning the NPS used their research boat to collect
a CTD cast using both their Seabird CTD and the C&C CTD to intercalibrate the
two instruments. A CTD cast is required to begin the patch-test procedure. A
sound-velocity profile was calculated from the cast and entered into the Simrad
software for refraction calculations and ray bending. The NPS collected CTD
casts several times a day for our soundvelocity profiles (SVP). The Surf
Surveyor departed the Wizard Island dock (Fig. 17) at 0900 hr to begin the
patch test. The initial patch test used the in-between mode over the flat basin
floor in the middle of the lake. Patch testing was completed by 1300 hr and the
survey began.
|
 |
|
Figure 17. RV
Surf Surveyor at Wizard Island dock. |
Saturday, July 29 (JD211)
The day was spent mapping the perimeter of the
lake as close to the shore as was possible. Mark Buktenica (NPS) was stationed
on the bow to guide the boat away from rocks.
Sunday, July 30 (JD212)
All day was spent running north-south lines
working from immediately east of Wizard Island toward the east. About 60% of the
lake was mapped. However, when the data tapes were downloaded, we discovered
that the navigation port was not sending navigation strings to the Simrad
software, which means the datagram recorded by the Hydromap software had no
navigation data. Fortunately, all the sensors, including navigation, are
recorded separately as well as integrated into the Hydromap datagram, so we had
navigation files. The problem was to reformat the DGPS data file so that it
would be accepted by the processing software. We spent all evening devising a
way to read in the DGPS GPGGA datagram into our processing software and finally,
at about midnight, were successful.
|
 |
|
Figure 18. Wizard Island field station for the
mapping project. |
The Wizard Island field station (Fig. 18) has a
diesel generator and a bank of batteries charged with a solar panel and an
inverter. We tested out the battery power by switching from the generator to the
batteries with only the two workstations online. The UPSs (uninterruptable power
supply) immediately started sounding alarms and one immediately shut off,
crashing one workstation. The second UPS switched to its internal battery and
allowed enough time to shut down the second workstation. The result of this test
was that all computers had to be shut down each night.
We also discovered that all of the offsets
between sensors had not been entered into the IMU (inertial motion unit)
software nor into the mergeNav script. All the data from Saturday and Sunday had
to be remerged with the appropriate offsets, then regridded and remosaicked.
Monday, July 31 (JD213)
The first thing Monday morning the generator
would not start. Consequently, we had no power to the computers. We discovered
that the generator the battery was dead. The battery was replaced and the
generator was restarted.
|
 |
|
Figure 19a. Chaski slide as seen from above lake
level. View looking southeast. |
Monday was “press day”; a morning that the press
was allowed on the water in the NPS RV Neuston to photograph the RV
Surf Surveyor actually mapping, as well as a visit to the field station on
Wizard Island. Most of the day was spent reprocessing Saturday and Sunday’s data
to correct for offsets and the navigation loss.
At 1245 hr the diesel generator powering the
workstations ran out of gas and only one UPS backed up a workstation; the other
UPS died, crashing the second workstation. Repeated efforts could not restart
the generator, apparently because of debris sucked into the fuel filter when the
diesel ran dry. Finally, at 1445 hr, with a cleaned fuel filter and diesel in
the tank, the generator started and we got back to processing data.
The entire day was spent trying to reformat the
various navigation files from Sunday’s data so that one of them could be read by
our processing software. Finally, near midnight, a fix was devised and tested.
The fix required reading the navigation file recorded by Hydromap.
|
 |
|
Figure 19b. Chaski slide as seen with no water in
Crater Lake. View is looking south. Chaski slide |
The mapping continued throughout the day and all
but a small deep-water area and some shallow-water areas were completed. Chaski
slide was entirely mapped and the below-water segment appears to be a debris
avalanche, similar to the one discovered in Lake Tahoe during the 1998 mapping
(Gardner et al., 2000). The area of the crater’s rim directly above the slide
has also failed and may be related to the below-lake failure (Fig. 19).
Tuesday, August 1 (JD 214)
The mapping commenced by circumnavigating the
lake twice to fill in data gaps and finally to beam-steer the transducer to
ensonify as close to the shore as possible. Sunday’s data were processed, then
Monday’s, and by 1000 hr the data processing was caught up with the data
collection.
Wednesday, August 2 (JD 215)
The day was spent filling in small gaps to insure
100% coverage. We collected the data tape at noon so that the processing could
be finished in the evening in time for packing the equipment van for an
early-morning departure. The final few hours of data collected in the afternoon
were quickly processed and the final maps (Figs. 12 and 13) were produced by
1800 hr.
The processing computers were shut down and the
equipment van was packed by 2100 hr.